SUB: Mana Badi : Nadu Nedu-Execution of the work  “Electrification with fans  and tube  lights” - guidelines  -issued-Regarding.

REF: G.  O.  Ms.  No.  87  of      the  School  Education  (Prog  -II)  department dated  30-11-2019.

    Government   vide   the   GO   read   in   the   ref     cited   have   accorded administrative  sanction  for  improving  the  School  Infrastructure  facilities  in all  the  schools  of  Phase  I  under  Mana  Badi  Nadu  Nedu  program. 

2.   The  primary  objective  of  this  work  is  to  provide  fans  and  tube lights  in  all  the  class  rooms  in  the  school.  Unless  we  do  proper  robust electrification,   we  cannot  fulfil  the  primary  objective.  The  life  of  the electrification   work   and   fans  should  be  75  years.  To  suit  to  these requirements,  we  need  to  follow  appropriate  standards  and  specifications given  under.    The  following  guidelines  shall  be  followed  in  taking  up  the work  ‘Electrification  with  fans  and  tube  lights’.

   i. If  there  is  no  electricity  for  the  school,  the  power  company  should  be approached.  And  necessary  costs  shall  be  met  from  the  program. However  pending  power  charges  for  the  school  shall  not  be  booked from  this  program.  The  same  shall  be  met  from  school  grant  being given  separately.

    ii. Concealed  Conduit  Wiring:
     a. Concealed  Conduit  Wiring  is  the  most  common  way  of  doing wiring  in  the  present  days.  The  same  shall  be  followed.
     b.Before  laying  the  PVC  pipes  in  the  wall, chasing/chiselling/grooving  shall  be  done  in  the  wall  with  wall cutters.  Avoid  manual  grooving  to  avoid  damage  to  the  walls.
     c. Conduits  (Pipes)  shall  be  fixed  inside  the  walls  with  approved clips  to  ensure  proper  routing  and  wiring.
     d. The  width  of  the  groove  shall  be  limited  as  per  the  number  of pipes/conduits.
     e. After   fixing   the  pipes,  boxes  and  accessories  the  groove surface  shall  be  filled  with  cement  mortar  and  chick  mesh wrapped  around  the  pipes.
     f. In  case  of  buildings  where  new  RCC  slabs/beams  are  laid,  the pipes  and  boxes  shall  be  provided  in  the  slab  portion/beam portion.

   iii.Surface  Conduit  Wiring:  Wherever  concealed  wiring  is  not  possible (Example:  crossing  of  RCC  columns,  Beams,  RCC  slabs)  go  for  PVC casing  and  capping  wiring  system  or  surface  conduit  wiring.

   iv.The  switch  boards  shall  be  fixed  at  appropriate  heights  and  at  equal heights  from  the  finished  floor  in  the  room.

v. All  the  class  rooms  shall  be  provided  with  3  phase  connection.

   vi.Wherever  fan  hooks  are  not  available  in  the  roof  slabs  fan  hooks shall  properly  welded  to  the  slab  reinforcement  at  equal  spacing.

   vii.Make  of  Tube  Lights,  Switches,  Sockets,  Ceiling  Fans  :  Crompton  / Philips  /  Havells  /  Legrand  /  Goldmedal  /  Policab  /  Bajaj  /  Wipro  / Usha  /  GEC  /  Orient.

   viii.The  supply  and  fixing  of  fans  will  be  done  by  the  firms  approved  at state  level  through  tender  system.

   ix.In  case  of  primary  /  upper  primary  schools  the  HM  shall  identify  the room  where  Smart  TV  to  be  installed  for  the  purpose  of  english  lab. In  such  room  we  need  to  put  a  separate  switch/plug  box  close  to  the wall  where  TV  to  be  fixed.

   x. For   the   purpose   of   electrical   pumps   appropriate   electrical arrangements  shall  be  taken  up  near  source  and  also  near  sump  (in case  of  booster  pump  is  used)

   xi.All  the  items  procured  locally  shall  be  checked  and  satisfied  before being  taken  to  the  site  :

       a. Brand  (as  notified)
       b. Rating
       c. Specifications
       d. Functioning  at  Standard  conditions e. Any  other  defects

3. The  specifications  of  the  materials  to  be  used  are  furnished  in  the annexure.

4.It  is  further  to  be  noted  that  the  supply  and  fixing  of  fans  will  be done  by  the  firms  approved  at  state  level  through  tender.

5. In  case  of  the  Demo  schools  procurement  of  fans  and  fixing  may  be taken  up  by  the  Parents  committee,  if  the  supply  process  gets delayed.

6. The  Parents  Committee  shall  procure  all  other  materials  other  than the  fans  in  the  market  duly  following  the  make  and  specifications and  take  up  the  fixing  through  Electrical  Mastery  (Electrical).

7. As  far  as  possible  the  electrician  rate  shall  be  finalised  on  turnkey basis  excluding  material  cost.  As  far  as  possible  avoid  paying  to electrician  on  daily  wages.

8. Hence  all  the  DEOs,  APCs  and  EEs  shall  make  note  of  the  guidelines and  specifications  of  the  material  and  ensure  proper  quality  in  taking up  the  Electrification  with  fans  and  tube  lights  work  and  complete them   within   the   specified   time.   This   work   shall   be   started immediately  if  not  started  already.

9. The  District  Collectors  are  requested  to  ensure  the  above  guidelines are  followed  and  quality  is  ensured  in  taking  up  Electrification  works under  Nadu  Nedu.

Share This:

Post Tags:

teacherbook.in

No Comment to " Mana Badi : Nadu Nedu-Execution of the work “Electrification with fans and tube lights” - guidelines "

  • To add an Emoticons Show Icons
  • To add code Use [pre]code here[/pre]
  • To add an Image Use [img]IMAGE-URL-HERE[/img]
  • To add Youtube video just paste a video link like http://www.youtube.com/watch?v=0x_gnfpL3RM